Rooftop Solar Approvals in Tamil Nadu: CEIG, NCES, TNPDCL and Generation Meter Explained
Getting rooftop solar approval in Tamil Nadu is often the slowest part of a solar project. Installing panels is the easy part. This guide explains each approval a rooftop solar project in Tamil Nadu may need, and how to avoid common delays.

Rooftop solar approval in Tamil Nadu: which approvals do you need?
Requirements depend on your system size, your tariff category (home, commercial or industrial) and whether you export power to the grid. In most projects, these are the approvals involved:
1. Net metering or net feed-in approval from TNPDCL (formerly TANGEDCO)
This lets your system connect to the grid. The application goes to the local electricity board office for your area. With net metering, the units you export are adjusted against the units you consume. With net feed-in, exports are paid at a fixed tariff. Which one you get depends on your consumer category.Net metering rules are set by the Tamil Nadu Electricity Regulatory Commission.
2. CEIG (Chief Electrical Inspector to Government) approval
CEIG checks that your installation meets electrical safety standards before it is energised. Larger systems usually need it.
Larger systems usually need it, and the capacity limit has been revised over time. Your installer or the local TNPDCL office can confirm whether your system needs CEIG approval.
3. NCES (Non-Conventional Energy Sources) approval
This covers registration and clearance for renewable energy generation under state norms. Whether it applies depends on your project type and size.
4. Solar generation meter approval
A separate generation meter records how much your system produces. It must be tested and sealed by the utility before commissioning.
Rooftop solar approval in Tamil Nadu: step-by-step process
- Site survey and design. Check shadow-free roof area, load and sanctioned demand.
- Apply for grid connectivity with the right documents (ID, EB bill, site plan, system details).
- Technical feasibility check by the utility.
- Installation after approval.
- CEIG inspection (if applicable), then meter testing and sealing.
- Commissioning and agreement signing.
Do not switch on the system before commissioning approval. Energising early can lead to rejection or penalties.Following this order keeps your rooftop solar approval in Tamil Nadu on track and avoids rework.
Five common reasons for delay
- Incomplete documents, such as a missing ownership proof or an outdated EB bill.
- Mismatch between sanctioned load and system capacity.
- Installation done before approval.
- Safety gaps found during inspection, such as earthing or protection devices.
- No follow-up. Applications can sit idle if nobody tracks them.
OPEX or CAPEX: how it affects approvals
Under CAPEX, you own the system and are responsible for the approvals (usually handled by your installer). Under OPEX, the solar provider owns, operates and maintains the plant, and manages the paperwork. Businesses that want less hassle often prefer OPEX. Those who want full ownership and long-term savings choose CAPEX.
Why use an installer who handles approvals
Many projects are delayed by paperwork, not by panels. At Kandhan Solar, we handle CEIG, NCES, TNPDCL and generation meter approvals along with installation and maintenance, so you deal with one team from start to commissioning.
Kandhan Solar manages rooftop solar approval in Tamil Nadu from application to commissioning.
Planning a rooftop or ground-mounted solar project in Chennai? Contact Kandhan Solar or call +91 90940 11042 for a free consultation.